When you are ready for operational testing, please send through pictures of the installation for the fire pump showing the following:   

  1. Power installed to the main control panel and jacking pump control panel 
  2. The exhaust system completed 
  3. Water turned on to the system 
  4. Batteries on site 
  5. Drainage from the fire pump completed 

When you are ready for operational testing, please send through pictures of the installation for the pump showing the following:  

  1.  ALL electrical wiring, connections and terminations to be completed by site electrician 
  2. Pump and float switch cables wired into control panel terminals by site electrician 
  3. In-tank installation of the pumps

DOWNLOAD THE SUBMERSIBLE COMPLIANCE GUIDE HERE


When you are ready for operational testing, please send through pictures of the installation for the pump showing the following:   

  1. ALL electrical wiring, connections and terminations to be completed by site electrician 
  2. Pump and float switch cables wired into control panel terminals by site electrician 
  3. In-tank installation of the pumps 
  4. The tank has water to at least 500mm above the pump/suction inlet 

When you are ready for operational testing, please send through pictures of the installation for the system showing the following:   

  1. Power point available 
  2. ALL electrical wiring, connections and terminations to be completed by site electrician 
  3. Plumbing completed 

Please also refer to this diagram which indicates OWS Hazard Zones and minimum distances.  

 

When you are ready for operational testing, please send through pictures of the installation for the pump showing the following:   

  1. Power installed to the main control panel
  2. Water is supplied to the pressure systems